Which can be Completed by 70 Men in 24 Days, Working 8 hours/day is :

If 90 men can do a certain job in 16 days, working 12 hours/day, then the part of that work which can be completed by 70 men in 24 days, working 8 hours/day is

  1. 5/8
  2. 7/9
  3. 1/3
  4. 2/3
Anurag Mishra Professor Asked on 25th October 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer is 7/9

    Monis Rasool Professor Answered on 28th October 2015.
    Add Comment
  • Your Answer