A and B undertake to do a piece of work for 6,000

A and B undertake to do a piece of work for 6,000. A alone can do it in 6 days and B alone can do it in 8 days. With the help of C, they finish it in 3 days. The share of C in the amount is

  1. Rs. 3,000
  2. Rs. 2,250
  3. Rs. 750
  4. Rs. 1,500
Anurag Mishra Professor Asked on 20th April 2016 in Maths.
Add Comment
  • 1 Answer(s)

    C’s 1 day work= 1/3 -(1/6 + 1/8)= 1/24

    A: B:C  (in terms of wages) = 1/6 : 1/8 : 1/24  = 4:3:1

    then  C’s share for three days is      :          (3*1/24  *6000)  =750