Then A alone can complete the whole work in :

In two days A, B and C together can finish ½ of a work and in another 2 days B and C together can finish 3/10 part of the work. Then A alone can complete the whole work in

  1. 15 days
  2. 12 days
  3. 14 days
  4. 10 days
Anurag Mishra Professor Asked on 27th December 2015 in Maths.
Add Comment
1 Answer(s)

Answer:  (4) 10 days

Explanation:-
A, B and C together can finish 1/2 of a work = 2 days
Therefore, A, B and C together can finish a work = 2 x 2
 = 4 days

B and C together can finish 3/10 part of the work = 2 days
Therefore, B and C can finish 3/10 part of the work = 10 x 2/3
 = 20 /3 days

So, A  alone can complete the whole work = 20/(5 – 3)
= 20 /2 
 = 10 days

Hence, the correct answer is option (4) 10 days. 

Anurag Mishra Professor Answered on 27th December 2015.
Add Comment