Then A alone can complete the whole work in :

In two days A, B and C together can finish ½ of a work and in another 2 days B and C together can finish 3/10 part of the work. Then A alone can complete the whole work in

  1. 15 days
  2. 12 days
  3. 14 days
  4. 10 days
Anurag Mishra Professor Asked on 27th December 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer:  (4) 10 days

    Explanation:-
    A, B and C together can finish 1/2 of a work = 2 days
    Therefore, A, B and C together can finish a work = 2 x 2
     = 4 days

    B and C together can finish 3/10 part of the work = 2 days
    Therefore, B and C can finish 3/10 part of the work = 10 x 2/3
     = 20 /3 days

    So, A  alone can complete the whole work = 20/(5 – 3)
    = 20 /2 
     = 10 days

    Hence, the correct answer is option (4) 10 days. 