A can Finish the Remaining Work in:

A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in :

  1. 3 days
  2. 5 days
  3. 7 days
  4. 11 days
Desire Adnan Default Asked on 4th August 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer:  (2) 5 days
    Explanation:-
    A can do a piece of work = 20 days
    Therefore, A can do work in a day = 1/20

    B can do the same work = 12 days
    Therefore, B can do the work in a day = 1/12

    B can do the work in 9 days = 9/12
    = 3/4
    Remaining work = 1 – 3/4
    = (4 – 3) /4
    = 1/4

    Then, A can finish the remaining work = 20 x 1/4
    = 5 days

    Hence, the answer is (2) 5 days.