A work could be completed in 100 days, However, due to the absence of 10 workers

A work could be completed in 100 days, However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was
(a) 100
(b) 110
(c) 55
(d) 50

Anurag Mishra Professor Asked on 29th February 2016 in Maths.
Add Comment
  • 1 Answer(s)

    Answer: (b) 110 

     

    Anurag Mishra Professor Answered on 4th March 2016.