In How Many Days B can Complete the Work

A’s 2 days’ work is equal to B’s 3 days’ work. If A can complete the work in 8 days then to complete the work B will take:

  1. 14 days
  2. 12 days
  3. 15 days
  4. 16 days
Monis Rasool Professor Asked on 29th August 2015 in Maths.
Add Comment
1 Answer(s)

Answer: (2) 12 days

Explanation:-
According to the question,
2 A =  3 B
Then,  B = 3 A/2

A can complete the work = 8 days.

Then, B can complete the work = 8 x 3/2
= 12 days

Then, B can  complete the work in 12 days.

Hence, the answer is (2) 12 days.