A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days before the completion of the work. In what time is the work finished?

  1.  14 days
  2. 10 days
  3.  9 days
  4. 12 days
Anurag Mishra Professor Asked on 26th October 2015 in Maths.
Add Comment
1 Answer(s)

Answer is 12 days

Monis Rasool Professor Answered on 28th October 2015.