In What Time is the Work Finished?

A, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days before the completion of the work. In what time is the work finished?

  1.  14 days
  2. 10 days
  3.  9 days
  4. 12 days
Anurag Mishra Professor Asked on 26th October 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer is 12 days

    Monis Rasool Professor Answered on 28th October 2015.
    Add Comment
  • Your Answer

    By posting your answer, you agree to the privacy policy and terms of service.