How Long will it Take to Finish the Work? If

3 men can do a piece of work in 6 days, 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?

  1. 3 days
  2. 5 days
  3. 2 days
  4. 4 days
vijay Professor Asked on 5th August 2015 in Maths.
Add Comment
1 Answer(s)

Answer: (1) 3 days

Explanation:-
3 men can do a piece of work = 6 days
Then, 1 man can do work in a day = /3 x 6
= 1/ 18
Therefore, 4 men can do the same work = 4/18
= 2/9

5 women can do the same work = 18 days
Then,  1 woman can do same work in a day = 1 /18 x 5
= 1 / 90
10 women can do the work = 10/ 90
= 1/9

4 men and 10 women work together in day = 2/ 9 + 1/ 9
= 3 / 9
= 1/3
Then, 4 men and 10 women work together can finish the work = 3 days
Hence, the answer is (1) 3 days.