How Many Men can Complete the Work? If

36 men can complete a work in 16 days. How many men will complete the same work in 24 days?

  1. 28
  2. 32
  3. 36
  4. 24
neeru Default Asked on 25th July 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer: (4) 24
    Explanation:-
    Formula-
    M1 x D1 = M2 D2
    Where, M – number of men & D – number of days.
    Here, M1 = 36 men, D 1 = 16 days, D 2 = 24 days & M 2 = ?
    Then, 36 x 16 = 24 x ?
    ? = 36 x 16 /24
    ? = 3 x 8
    ? = 24 men
    Hence, 24 men will complete the same work in 24 days.

    Anurag Mishra Professor Answered on 26th July 2015.