Find the Difference of Days in Which R and P can Complete the Job :

P and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days, P started the work and worked for 3 days. Q and R continued for 6 days, Then the difference of days in which R and P can complete the job is

  1. 10
  2. 15
  3. 12
  4. 8
Anurag Mishra Professor Asked on 26th October 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer is (1): 10

    Monis Rasool Professor Answered on 28th October 2015.
    Add Comment
  • Your Answer

    By posting your answer, you agree to the privacy policy and terms of service.