What would be the total factory overhead rate?

Consider an industry with the following features:
> Budgeted monthly fixed cost=Rs.2,20,000
> Normal monthly output= 12000 per standard labour hour
> Standard variable overhead rate = Rs.25 per labour hour
What would be the total factory overhead rate?
(a) Rs.40.33 per labour hour
(b) Rs.41.67 per labour hour
(c) Rs.42.67 per labour hour
(d) Rs.43.33 per labour hour

Anurag Mishra Professor Asked on 12th January 2016 in Maths.
Add Comment
  • 1 Answer(s)

    Answer: (d) Rs. 43.33 per labour hour 

    Anurag Mishra Professor Answered on 12th January 2016.
    Add Comment