20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined them. In how many more days is the work completed?

  1. 12
  2. 14
  3. 15
  4. 13
Monis Rasool Professor Asked on 8th July 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer: (1) 12 days
    Explanation:-
    20 men can do piece of work = 18 days
    20 men can do work in a day = 1/18
    Therefore,  20 men can do work in 3 days = 3/18 = 1/6
    Remaining work = 1 – 1/6 = 5/6
    5 men joined them
    Then, the number of men = 20 + 5 = 25
    25 men can do work in a day = 6 x 25/18 x 20 x5 = 1/12
    25 men can do work complete =  12 days
    Hence, the answer is (1) 12 days.