In How Many Days was the Work Done? If

A, B and C can do a piece of work in 24, 30 and 40 days respectively. They began the work together, but C left 4 days before completion of the work. In how many days was the work done?

  1. 13
  2. 14
  3. 11
  4. 12
Monis Rasool Professor Asked on 28th August 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer:  (1) 13 

    Explanation:-
    A can do a piece of work =  24 days
    Therefore, A can do work in a day = 1/24

    B can do the same work = 30 days
    Therefore, B can do work in a day = 1/30

    C can do the same work = 40
    Therefore, C can do the work in a day  =1/40

    Then, C can do work in last 4 days = 4/40
    = 1/10

    Then, the remaining work = 1 – 1/10
    = (10 – 1)/10
    = 9/10

    Time taken by A, B and C to complete the remaining work = 9 x (24 x 30 x 40)/10 x (30 x 40 + 24 x 40 + 24 x 30)
    = 9 x 24 x 1200/28800
    = 9

    Total time taken to complete the work = 9 + 4 = 13 days.

    Hence, the answer is (1) 13 days.