Y can Alone Finish that Work in:

X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in:

  1. 42 days
  2. 18 days
  3. 27 days
  4. 36 days
Anurag Mishra Professor Asked on 17th November 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer:  (4) 36 days

    Anurag Mishra Professor Answered on 17th November 2015.
    Add Comment
  • Your Answer

    By posting your answer, you agree to the privacy policy and terms of service.