How Many Men Needed to Complete a Job? If

How many men need to be employed to complete a job in 5 days, if 15 men can complete 1/3 of the job in 7 days ?

  1. 20
  2. 21
  3. 45
  4. 63
Manish Listener Asked on 18th June 2015 in Maths.
Add Comment
  • 1 Answer(s)

    Answer: (4) 63
    Explanation:-
    15 men can complete 1/3 of the job = 7 days
    15 men can complete the job = 3 x 7 = 21 days

    Let be the X men complete the job in 5 days
    Then, X = 15 x 21/5 = 63 men
    Hence, the answer is (4) 63

    Anurag Mishra Professor Answered on 19th June 2015.